The Wenham Planning Board met at Wenham Town Hall and via Zoom on July 8, 2026, to discuss Select Energy’s petition for a large-scale solar installation at 91 Grapevine Road on the Iron Rail property. Key issues included National Grid’s conditional approval, proposed site-plan changes, and the timing of the decommissioning bond. Pending a complete application and further analysis, the board continued the hearing to August 12, 2026. The board also endorsed an updated Approval Not Required plan for 7–9 Maple Street involving Greenbelt and One Tree LLC and reviewed edits to the subdivision regulations.